A formal document issued by a contracting authority to record and authorise a change to an existing public contract, capturing the nature, scope, cost, and approval of the amendment.
A Contract Change Notice (CCN) is the formal instrument used to record, approve, and implement a variation to a live public contract. It creates an auditable paper trail from the initial request for a change through to its authorisation and incorporation into the contract baseline. Without a CCN, changes can be disputed, uncosted, or legally vulnerable.
Under the Procurement Act 2023 (which replaced the Public Contracts Regulations 2015 for most above-threshold contracts), modifications to existing contracts are tightly controlled. Material changes — broadly, those that alter the economic balance in favour of the supplier, extend scope substantially, or would have attracted different bidders — may constitute a new procurement if not covered by a recognised modification ground (Schedule 8 of the Act). A CCN must therefore reference the legal basis under which the change is permitted, whether that is a contract modification clause, a below-threshold adjustment, or an unforeseen circumstance provision.
For contracts above the relevant thresholds, authorities must publish a Contract Change Notice on the Find a Tender Service (FTS) or, from October 2024, on the new central digital platform, within 30 days of making a qualifying modification.
Poorly managed contract changes are a persistent finding in audits by the National Audit Office and Cabinet Office spend reviews. Undocumented changes expose the authority to disputes over scope, additional cost, or supplier under-performance. A CCN:
Most contracting authorities require a CCN to pass through a change control board or senior responsible owner before signature. Thresholds for escalation (e.g. changes above £50,000 requiring Director sign-off) should be set out in the authority's contract management framework.