DoF - Collaborative Arrangement - Provision of Metered Electricity 2027-2030
This contract will be for the supply of 100% renewable (green) Metered Electricity for a term of 36 months. The anticipated commencement date shall be 1st April 2027 and expire on 31st March 2030.
Suppliers should refer to the Specification Schedule for full detail on the requirements of this contract. A list of participating bodies can be found in this document.
The IF109 Framework is being established to support delivery of NI Water's capital investment programme and will succeed the existing IF105 Integrated Partnerships Framework, which is due to expire in May 2028. The Framework is intended to support delivery of the PC28 investment programme and future regulatory periods whilst securing the capacity, capability, flexibility, value for money and resilience required to deliver NI Water's future capital programme.
The IF109 Integrated Partnerships Framework will support a range of works and related services including programme and project management, design, engineering, construction, commissioning and other supporting or ancillary activities necessary to support the successful delivery of NI Water's capital investment programme.
The Framework is intended to support delivery of NI Water's future investment priorities, including regulatory compliance, service improvement, resilience enhancement, environmental performance and long-term sustainability objectives.
The IF109 Integrated Partnerships Framework comprises four Lots covering:
Lot 1 - Minor Civil Pipelaying Works
Lot 2 - Minor Civil Works
Lot 3 - Minor MEICA & Process Works
Lot 4 - Major Civil, MEICA & Process Works
Together, these Lots will support the delivery of projects ranging from small-scale network investment and rehabilitation activities through to large-scale, complex, multidisciplinary capital programmes across NI Water's water and wastewater asset base.
The Framework has been designed to support long-term delivery of NI Water's investment programme whilst providing the flexibility required to respond to evolving programme, funding and operational requirements throughout its duration.
The total framework value may be shared across all Lots.
View 4-notice timelineLatest notice released 18 Nov 2026
Private SectorTender
SONI090 – Client-Side Advisor
SONI is seeking to appoint one (1) supplier to act as Client-Side Advisor, providing programme management, technical assurance, test assurance and transition support to SONI in respect of the Corporate IT Separation Programme and the establishment of SONI’s Security Operations Centre, working alongside SONI’s internal programme and technical teams. This procurement is being conducted in accordance with the Procurement Act 2023 (the “Act”) and the Procurement Regulations 2024.
The Client-Side Advisor augments SONI’s own programme and technical team, providing programme leadership, technical assurance and delivery oversight of the Systems Integrators (SIs) and suppliers delivering the separation workstreams. The role does not extend to the delivery, implementation or provision of any of the underlying systems, equipment or services being procured under SONI’s other separation competitions.
The Tenderer awarded the Framework Agreement (the ‘Supplier’) will act as SONI’s primary partner for Client-Side Advisory services, working alongside SONI’s internal teams and its other external advisors.
Department of Finance (DoF) have a requirement for the support, maintenance and development of the existing Identity Assurance (NIDA) application, and associated Digital Identity Verification services. The contract will be for a service transition and implementation period of up to 3 months, followed by an initial period of 3 years from service commencement, with two further options to extend by up to 1 year each. Suppliers should refer to the Specification Schedule for full detail on the requirements of this contract.
T26-142CAP Strabane Leisure Centre and Road Realignment (Design and Construct) Preliminary Market Engagement
Derry City and Strabane District Council intend to commence a robust, credible and transparent preliminary market engagement exercise to develop a deliverable and affordable option for Strabane Leisure Centre in order to achieve a successful contract award by June 2027. The purpose of this preliminary market engagement (PME) is to gather insights and feedback from the market to inform the development of the procurement strategy and specification for Strabane Leisure Centre and road alignment as well as assisting Derry City and Strabane District Council to ensure that the most efficient and effective methods of procurement are considered. The first phase of the market engagement exercise will be participation from the supply base through the attached questionnaire. Responses to these questions will help Derry City and Strabane District Council gather comprehensive information about potential suppliers and the services they offer. This will allow us to make informed decisions regarding our specification and procurement strategy before entering the market with a full procurement competition. At this stage, any information gathered through this engagement exercise will solely inform internal business planning and any possible subsequent procurement process; and will NOT be appraised in any future tender evaluation exercise. Please note that participation or non-participation in this preliminary market engagement shall not prevent any provider participating in any potential procurement process, nor is it intended that any information supplied shall place any provider at an advantage or disadvantage in any forthcoming procurement process. In responding, it is important to note that detailed and lengthy submissions are not necessary at this stage and generic marketing material is not required. Nonetheless, we welcome any pertinent information on your company’s capability and views on the range of services required. **PLEASE NOTE: ALL COMPLETED QUESTIONNAIRES MUST BE SUBMITTED VIA THE eTendersNI PortaI.*** Respondees are not required to wait until the closing date to submit a response. PME QUESTIONNAIRE RESPONSES MAY BE SUBMITTED VIA THE ETENDERSNI CFT MESSAGING FACILITY AT ANY TIME UP TO 12:0 on 20th November2026***
Derry City and Strabane District CouncilNorthern IrelandWAC-687078
Non Invasive Ventilation, Associated Consumables and Ancillary Services in the Community
This Framework Agreement is being established on behalf of Health and Social Care (HSC) in Northern Ireland (referred to as ‘the Buyer’).
The aim of this Tender is to develop a regional managed service to provide for the health and wellbeing of Patients who have been prescribed NIV Treatment. HSC organisations are committed to maximising the social value available through this procurement, by collaborating with the Suppliers to address identified social and health inequalities which exist for Patients within the scope of this managed service.
Belfast Health & Social Care TrustNorthern IrelandWAC-686712
TRIANGLE HOUSING ASSOCIATION CRAIGAVON LAND, DESIGN AND BUILD COMPETITION OCTOBER 2026
Provision of suitable land and the design and construction of 15-25 units of social rented housing in Craigavon (Northern Ireland) meeting the standards laid down in the housing association guide of the Department for Communities NI.
C280 (2027) Supply Low Voltage Cable Jointing Systems
Northern Ireland Electricity Networks Limited (NIE Networks) intends to establish a framework arrangement under which it shall appoint suppliers to enter into separate framework agreements for C280 (2027) Supply Low Voltage Cable Jointing Systems. It is anticipated that each framework agreement awarded will be for a period of five (5) years with an option, exercisable entirely at the discretion of the contracting authority and subject to the terms of the framework agreement, to extend by a further optional period of up to three (3) years, with a total potential duration of eight (8) years.
NIE Networks estimates that the total spend under framework agreements could be up to £15.5 million over the total potential eight-year duration.
Therefore, NIE Networks is conducting a Preliminary Market Engagement (PME) supplier information event to gather insights from the market before initiating a procurement process for Contract C280 (2027) Supply Low Voltage Cable Jointing Systems.
This engagement aims to assess the market's interest and capabilities in delivering Contract C280 (2027), identify potential solutions and develop an effective procurement strategy. NIE Networks anticipates an ongoing requirement for resin compounds, insulation compounds, joint shells and complete low voltage cable jointing systems. Through this engagement, NIE Networks also wishes to understand developments within the market and identify any innovative products, technologies or approaches that could provide additional benefits in areas such as safety, reliability, installation efficiency, sustainability and security of supply.
NIE Networks currently utilises a range of Low Voltage Cable Jointing Systems across its distribution network. While these products will continue to form a core part of operational requirements, NIE Networks is keen to engage with the market to understand emerging technologies, product developments and best practices that may complement or enhance existing solutions.
View 2-notice timelineLatest notice released 31 Dec 2026
Public SectorTender
Personal Protective Equipment 2884208
Business Services Organisation (BSO) Procurement and Logistics Service (PaLS), on behalf of all Northern Ireland Public Sector Bodies covered by the Northern Ireland Public Procurement Policy (NIPPP), is establishing a Dynamic Purchasing System (DPS) for the procurement of both disposable and re-usable Personal Protective Equipment (PPE) and other Associated Products. The DPS may also be used to procure other variants from time to time. The HSC Business Services Organisation (BSO) Procurement and Logistics Service (PaLS) invites you to respond to this DPS. If you wish to communicate with the buyer, please do so by using the secure messaging area relevant to this DPS within the eTendersNI portal.
Regional Business Services Organisation, Procurement and Logistics ServiceNorthern IrelandWAC-456430
Change to Period of Validity of existing Dynamic Purchasing System (DPS) for The Supply of Services Relating to the Treatment and Energy Recovery/Disposal of Residual Waste Arisings - Extension to 23 February 2029
On 5 August 2022, arc21 published notice 2022/S 000-021639 (the "Notice") concerning the establishment of arc21's Dynamic Purchasing System (DPS) for its ongoing requirement for the supply of services relating to the Treatment and Energy Recovery/Disposal of Residual Waste Arisings.
The DPS was initially established on 27 October 2022. The period of validity stated in the Notice was for an initial period of 48 months (i.e. until 27 October 2026), but the Notice stated that the DPS was anticipated to remain live for a further 48 months after this.
The purpose of this notice is to record that the period of validity of the DPS has been changed by extending the period of validity to 23 February 2029 (so that the period of validity of the DPS is from 27 October 2022 to 23 February 2029).
The DPS is divided into four (4) Lots, for the provision of services relating to the treatment and energy recovery or disposal of Member Councils' residual waste arisings:
Lot 1 predominantly incorporates residual kerbside collections and residual waste from commercial/trade collections, which may be mixed with other residual waste streams.
Lot 2 predominantly incorporates residual waste from Household Waste Recycling Centres which may be mixed with other residual waste streams.
Lot 3 predominantly incorporates combined residual kerbside waste from commercial/trade collections and Household Waste Recycling Centre waste which may be mixed with other residual waste streams.
Lot 4 predominantly incorporates other residual waste streams such as street litter, bulky waste and fly tipped waste and which may include waste arising from bonfires that has not or cannot be combined in any of the Lots.
Within each of the Lots there may also be a requirement for the Contractor(s) to provide a delivery point(s) within a specified range; the loading of waste and/or an element of waste transport.
The DPS is a two-stage process. There is no intention to limit the minimum and maximum number of service providers. The DPS will be open to entrants, throughout its life, who meet the minimum criteria. Further information on the selection process can be found within the procurement documents. In addition to the specific Participating Bodies detailed in the notice, Call-Off Competitions may include waste from NI Councils who are not constituent councils of arc21.
For previous information regarding this DPS, please refer to the original Contract Notice reference: 2022/S 000-021639, https://www.find-tender.service.gov.uk/Notice/021639-2022?
For the avoidance of doubt, Economic Operators that have already had Applications accepted under the DPS do not need to respond to this Contract Notice as they are already admitted to the DPS under their respective Lots.
SONI095 Managed Service - Security Operations Centre
SONI intends to procure a single Supplier to deliver the SOC (Managed Service - Security Operations Centre) Services, as one tier of a multi-tiered security environment, operating fully within SONI owned tooling and SIEM for the provision of the managed SOC. Detailed service, architecture, tooling, telemetry, integration, governance, performance and contractual requirements will be provided at tender stage under NDA.
Following completion of this PSQ stage, up to 3 suitably qualified Candidates will be shortlisted and invited to participate in the tender stage. The tender process will result in the selection and appointment of a single Supplier who will be responsible for delivering the Services for the duration of the contract.
This document outlines the structured process being used by SONI in the selection of suppliers for the provision of Software Licensing & Buying Services. This document provides a description of the services we wish to procure.
The purpose of the RFP is to invite detailed proposals from interested parties (Tenderers) for the provision of said services.
This RFP document together with all supporting requirement documents contains detailed information required by the Tenderer to submit a valid tender proposal. Tenderers are requested to respond to all areas and requirements specified in these documents.
1. Preliminary Market Engagement
Mid and East Antrim Borough Council intends to undertake Preliminary Market Engagement (PME) in advance of a proposed procurement exercise for the construction of the i4C Innovation & Cleantech Centre in Ballymena.
The purpose of this Preliminary Market Engagement is to engage with suitably experienced contractors and the wider construction market to assist the Council in developing and refining its procurement strategy and approach prior to commencement of the formal procurement process.
The Council wishes to understand current market capability, capacity and appetite for a project of this nature and to obtain market feedback on matters which may influence the final procurement and delivery strategy.
2. Project Description
The proposed i4C Innovation & Cleantech Centre will provide a purpose-designed innovation and cleantech facility in Ballymena, supporting businesses operating within the clean technology, innovation and advanced manufacturing sectors.
The proposed development is anticipated to comprise office, collaboration and innovation spaces together with light industrial/workshop accommodation, ancillary facilities and associated external works, access, parking, landscaping, utilities and infrastructure.
The current estimated construction contract value is approximately £20 million, inclusive of allowances for construction and design risk and anticipated construction and tender inflation. This figure is indicative only and remains subject to ongoing design development, cost planning and confirmation of the proposed procurement scope.
The inclusion of loose furniture within the construction contract remains under consideration and will be confirmed as the procurement strategy is developed.
The project is currently progressing through design development and statutory approval stages. The
The project is currently progressing through design development and statutory approval stages. The final scope and procurement documentation remain subject to development and approval.
Through this Preliminary Market Engagement exercise, the Council is seeking feedback from the construction market in relation to matters including, but not necessarily limited to:
•
current contractor interest and appetite for the project;
•
market capacity and anticipated competition;
•
proposed procurement and contracting approach;
•
appropriate tendering and construction programme durations;
•
buildability and potential construction sequencing considerations;
•
key project and delivery risks;
•
current supply-chain constraints and lead-in periods;
•
inflation and other relevant market conditions;
•
opportunities for early contractor or supply-chain input;
•
sustainability and environmental requirements, including the proposed BREEAM objectives;
•
social value and opportunities for local supply-chain and SME participation;
•
information that tenderers would require to appropriately understand, price and manage the project risks; and
any other matters which respondents consider could improve the deliverability, value for money or procurement of the project.
The Council may use information obtained through this exercise to inform the procurement strategy, tender documentation, programme, risk allocation and other aspects of the proposed procurement
Interested contractors are invited to participate in the Preliminary Market Engagement exercise.
Participants will be asked to provide feedback through Appendix A – Preliminary Market Engagement Questionnaire.
The relevant Preliminary Market Engagement information and questionnaire will be made available through https://e-sourcingni.ukp.app.jaggaer.com/.
Interested contractors are invited to review the information provided and submit their completed responses through the portal no later than:
•
Monday 16th November 2026 at 5pm
Indicative Procurement Programme
The following dates are indicative only and may be subject to change:
•
Preliminary Market Engagement Notice published: Tuesday 20th October 2026
•
Deadline for PME responses: Monday 16th November 2026
•
Formal procurement process anticipated to commence (PSQ): January 2027
•
Invitation to Tender (ITT) anticipated: June 2027
•
Contract award anticipated: December 2027
•
Contract commencement anticipated: February 2028
•
Construction commencement anticipated: May 2028
•
Contract completion anticipated: December 2029
Appointment of Integrated Supply Team for St Conor’s College, 11 Bann Road, Kilrea
The appointment of an Integrated Supply Team for the delivery of new St Conor’s College on existing Kilrea site. The appointment includes enabling works for decant to the Clady site and demolition of both existing School buildings. The proposed project will establish a state-of-the-art post-primary school for 730 pupils on the existing 4.26-hectare Kilrea site. The building will comply fully with DENI handbook standards and include modern teaching facilities, School Meals Accommodation (SMA). The area of the site is below the area recommended by the DENI Handbook, the shortfall is evident in the proposed sports provision.
Translink” is establishing a Framework for the provision of Project Management, Technical Support and Business Change Services to support Rail Systems, Engineering and Operations projects across the Translink rail network and associated assets. The Framework will provide access to specialist consultancy, advisory and embedded resource support to assist with the development, delivery, implementation and optimisation of rail projects and programmes
PRE-MARKET ENGAGEMENT QUESTIONNAIRE (PME) for Ambient and Chilled Grocery Products for Education Authority NI
The Education Authority Northern Ireland (EANI) wishes to engage with the market to seek their views on establishing a robust, value for money contract for the provision of Ambient and Chilled Grocery Products and Fresh Muffins. Any information gathered through this market consultation exercise will inform internal business planning and any possible subsequent procurement process and will NOT be appraised in any future tender evaluation exercise. Please note that participation or non-participation in this preliminary market consultation exercise shall not prevent any supplier from participating in any potential procurement process, nor is it intended that any information supplied shall place any supplier at an advantage or disadvantage in any forthcoming procurement process. For the avoidance of doubt, this is the scoping phase of the project and is not part of a formal procurement process. Suppliers who wish to participate in the market engagement exercise should complete the pre-market engagement questionnaire. Further information including the questionnaire can be downloaded from CfT documents. The Questionnaire must be completed no later than 3pm on the closing date detailed in the PME Questionnaire document. There are no formal tender documents to be completed other than the questionnaire.
BHC is seeking expressions of interest from the contractors who are interested in tendering for the construction of a proposed three-storey extension to the existing Operations Engineering Workshop to provide a replacement Port Operations Control Centre, incorporating office accommodation and staff welfare facilities and all associated site works. The approximate Gross Internal Area is 1,155sqm.
Further information regarding this opportunity is available within the pre-qualification documents available at the weblink provided in this notice.
PRE-MARKET ENGAGEMENT QUESTIONNAIRE (PME) for CAT-26-002 Sustainable Catering Disposables and Packaging
This is not a tender exercise by the Education Authority. The Education Authority Northern Ireland (EANI) wishes to engage with the market to seek their views on establishing a robust, value for money contract for the provision of sustainable catering disposables and packaging products . Any information gathered through this market consultation exercise will inform internal business planning and any possible subsequent procurement process and will NOT be appraised in any future tender evaluation exercise. Please note that participation or non-participation in this preliminary market consultation exercise shall not prevent any supplier from participating in any potential procurement process, nor is it intended that any information supplied shall place any supplier at an advantage or disadvantage in any forthcoming procurement process. For the avoidance of doubt, this is the scoping phase of the project and is not part of a formal procurement process. Suppliers who wish to participate in the market engagement exercise should complete the pre-market engagement questionnaire. Further information including the questionnaire can be downloaded from CfT documents. The Questionnaire must be completed and PME Document signed and returned via the Messaging function of eTendersNI by no later than 3pm on Wednesday 21 October 2026 (deadline) in accordance with the instructions detailed in the PME Questionnaire document. There are no formal tender documents to be completed other than the questionnaire.
Competitive Land Design and Build Contract within NIHE area Lisburn, Northern Ireland
In order to fulfil its development programme, the Contracting Authority is seeking to appoint developers to provide land for the development of social housing.
The Contracting Authority seeks land in Lisburn, Northern Ireland. In the interests of providing an efficient housing management service, the Contracting Authority will not consider Sites which provide more than 70 units or less than 50 units. Preferably units are to be delivered at a single Site, however, adjacent sites maybe considered.
RAD226 - SOCIAL HOUSING CONSTRUCTION PROJECT AT WOODSIDE ROAD, DERRY
Woodside Road, Derry/Londonderry
The proposed construction works contract is for the construction of a residential development on a greenfield site on the Woodside Road, Derry/Londonderry. The works is for the provision of 57 social housing units that includes a housing mix of 45 homes including split level units, 4 wheelchair accessible homes and 8 apartments including 1 wheelchair accessible. The site also includes extensive landscaping, a children's play park, amenity space and other ancillary works. Alongside the 57 units, a programme of site wide enabling works will also be undertaken.
The complexity of this development includes site clearance, site remodelling due to site topography, utility alterations, construction of a bus turning circle and detailed phasing requirements.
It is expected ALL social housing units built under this contract will achieve Secured by Design and Lifetime Homes accreditation. All units will also be required to achieve EPC Rating 'A'. The project will also be delivered to BIM Level 2.
A Planning Application, reference LA11/2022/0681/F, for the project was submitted to Derry City & Strabane District Council in June 2022. Full approval is expected in the coming months.
The contract will be for approximately 24-months from date of award and is scheduled to start in March 2027 with the ITT documentation being issued in December 2026.
Time is to be of the essence in delivering the works and any failure by the Contractor to comply with the time limits for commencing or completing the works shall be deemed to be a substantial failure by the Contractor to comply with the contract giving the Employer a right to terminate the contract.