GRIP 5-8 Delivery of Coventry South, Northampton CET and Tyseley Fuel Road 12
WM Trains Limited is procuring rail depot and servicing works through one advertised works procurement structured in two contractual stages.
Stage 1: PCSA
Under the Pre-Construction Services Agreement (PCSA), the contractor will complete the GRIP 5 design, further develop the design, and price the individual works packages.
Stage 2: ECC
Once those package prices have been developed and consolidated into a single commercial position, the project will proceed to award the NEC4 Engineering and Construction Contract (ECC) on a lump-sum basis for GRIP stages 6 - 8.
The procurement is intended to appoint a contractor for each Lot to provide Stage 1 PCSA services. Stage 2 may follow, subject to the contracting authority's decision, funding, approvals and procurement compliance requirements. The contracting authority does not commit by this notice to award Stage 2.
Please note that it may not be necessary for the successful bidder for each Lot at Stage 1 to undertake all of the GRIP 5 design required for that particular Lot as some elements of the GRIP 5 design may already have been completed by tender award stage. If that is the case, it would be expected that the successful bidder would inherit any GRIP 5 design already completed for a particular Lot and then use that to inform the remainder of the GRIP 5 design required for that particular Lot.
The procurement is divided into the following Lots:
Lot 1 - Coventry Carriage Sidings Stabling and Servicing Facility
Lot 2 - Northampton Riverside CET
Lot 3 - Tyseley Road 12 Permanent Fuelling Apron
Tenders may be submitted for one, more than one, or all Lots, subject to the instructions in the associated procurement documents available at https://www.delta-esourcing.com/respond/EHTJX59C3V.
For more information about this opportunity, please visit the Delta eSourcing portal at:
https://www.delta-esourcing.com/tenders/UK-UK-Birmingham:-Railway-depot-construction-work./EHTJX59C3V
To respond to this opportunity, please click here:
https://www.delta-esourcing.com/respond/EHTJX59C3V
Please note that the contract start and end dates given for each Lot are provisional and are to be agreed following submission of programmes at the ITN stage. The dates are purely draft and are a guide only ahead of the procurement commencing and may be considerably longer than stated. The start date for each Lot may vary dependent on the availability of GRIP 4 design and not all contracts may be awarded at the same time and not all ITN's issued at the same time following shortlisting at the PSQ stage.
This contract is for the delivery of a new proposed tank wagon loading and unloading facility to works at Tyseley Fuel Road 12
The project will be procured under a two stage approach.
The initial stage will be the award of a Pre- Construction Agreement (PCSA) for GRIP 5.
Upon successful completion of the PCSA (GRIP 5) , the contracting authority will evaluate the detailed design and cost plan with a view to negotiating a separate works contract for GRIP Stages 6 to 8. The PCSA itself does not guarantee award of the full construction phase