The proposed Bus Services Framework is being established to support the future procurement of a wide range of bus and passenger transport services. These include secured local bus services, schools and works transport, group travel, seasonal services, Metro replacement services, and other operational or emergency transport requirements. The framework will operate as a closed framework agreement for an initial three-year period, with the option to extend for up to 24 months. The total estimated framework value is up to £200 million across the potential five-year term.
Nexus currently spends around £20 million each year on bus service contracts procured through a number of separate tendering exercises. The new framework aims to provide a more efficient and flexible procurement route, reducing the need for repeated procurements while maintaining competition and supporting effective service delivery.
Tyne and Wear Passenger Transport Executive T/A NexusWAC-643927
Nexus are looking for a design and build contract to undertake the improvement of existing facilities at South Gosforth Control Centre for staff to create a fit for purpose working environment.
The aim of the project is to improve the existing facilities at South Gosforth Control Centre for staff to create a fit for purpose working environment. The building was constructed in 1980 and has undergone limited refurbishment in 2014 and 2021/22. There is a requirement for a more flexible working environment and improved welfare facilities from users to align with Nexus Places principles. However, following investigations of the structure and its systems several assets require renewal or upgrades to achieve compliance, including security measures. The Control Centre must remain operational 24/7 during the project.
We are looking for a contractor to undertake the design and build contract for the refurbishment of the Control Centre.
Scope requirements
The preliminary scope requirements for the Control Centre refurbishment are:
Accessibility improvements for movements to and around the building (not including the provision of a lift)
Traffic management and street furniture improvements
Roof and roof safe access improvements
Drainage system improvements
Fire detection and protection improvements
Lighting, high voltage and low voltage systems upgrades
Ventilation and gas suppression system upgrades
M&E provisions for upgrades to welfare facilities
Security system upgrades (inc. CCTV)
Removal of internal walls and installation of glass partitions and soundproofed internal walls
Improvements to canteen and welfare facilities
Provision for additional meeting rooms, breakout areas and desks
Improvements to ICT systems and provisions for user usage
A supplier is required to carry out a design and build contract for the refurbishment of the Control Centre.
The Control Centre must remain operational 24/7 during the project.
Tyne and Wear Passenger Transport Executive T/A NexusWAC-639137