Homes England - Construction of Primary School - Brookleigh
Homes England are issuing this notice in relation to the construction of Brookleigh Primary School, located to the north of Burgess Hill within the County of West Sussex. The school site forms a parcel of land within a wider development at Brookleigh (also known as Northern Arc). Brookleigh is intended to deliver 3,500 homes, as well as other non- residential uses including the school.
The anticipated start on site is January 2028 with a 19-month construction period, with the school ready for the start of the Autumn term September 2029 and the outline scope of works is to include the following;
• Primary School building incorporating classrooms, halls, studios, dining and kitchen area, learning resources (including library), staff and administration areas, storage areas, toilets, front of house and back of house areas, etc.
• External Works including hard and soft landscaping, sports pitches, canopies, boundary walls, etc.
Outline planning consent for Brookleigh was granted in October 2019 (reference DM/18/5114) and Resrved Matters decision May 2026 (reference DM/25/2640) . Further details can be found by on ProContract, Homes Englands eTendering portal.
Homes England (the name adopted by the Homes and Communities Agency)WAC-640768
Homes England - Demolition of former Halfway House Primary School - Isle of Sheppey
Homes England intends to appoint a suitably qualified and experienced contractor to undertake the demolition and associated enabling works at the former Halfway Houses Primary School, Queenborough Road, Minster-On-Sea, Isle of Sheppey ME12 2BE.
The scope of works is anticipated to include
• Site establishment, mobilisation and security arrangements.
• Soft strip of existing school buildings and structures.
• Identification, removal and lawful disposal of asbestos-containing materials, including independent verification and monitoring requirements.
• Demolition of all existing buildings (B1-B7, B9 and B10), structures and associated infrastructure to ground level floor slabs.
• Protection, isolation and management of existing private services.
• Management of ecological constraints, including compliance with protected species (bat) mitigation measures and site-specific ecological requirements.
• Processing, segregation, recycling and disposal of demolition arisings and waste materials.
• Environmental monitoring and control measures, including dust, noise and vibration.
• Site clearance and preparation of the site for future redevelopment.
• Provision of all completion records, waste documentation, statutory compliance records and handover information required under the contract.
The successful contractor will be required to undertake the works in accordance with all relevant statutory requirements, health and safety legislation, environmental controls, ecological constraints and the requirements of the NEC3 Engineering and Construction Contract (Option A). At the time the procurement documentation was prepared, the application remained under consideration by the Local Planning Authority. Tenderers will be expected to comply with any planning conditions, mitigation measures or statutory requirements arising from the Prior Approval process. The principal objective is to safely demolish the former school, remove asbestos-containing materials, clear the site and deliver a development-ready parcel of land to facilitate Homes England's future redevelopment aspirations for the site.
All dates and values in this notice are indicative and may be subject to change.