Castle Point Borough Council (CPBC) through the Essex Procurement Partnership (EPP) is looking to renew their recycling waste disposal services contracts.
This relates the provision of a waste transfer station (WTS), haulage and Materials Recycling Facility (MRF) services for the borough's dry mixed recycling requirements (excluding glass).
The contract duration is 5 years plus an optional extension of up to 5 years in one or multiple increments.
Known-unknown risks:
1- Declining or failing end markets
Impact: Financial pressure, operational disruption, and performance risks for both the Contractor and the Authority.
Why this cannot be addressed upfront: Neither party can accurately forecast long‑term end‑market viability or values, making upfront risk pricing potentially disproportionate and poor value for money.
2- Geopolitical events / Wars / Blockades
Impact: Service delays, reduced recycling performance, financial pressure on the Contractor, or value‑for‑money risks for the Authority
Why this cannot be addressed upfront: Pricing, service volumes, and operational impacts cannot be accurately or proportionately quantified at contract inception without introducing excessive risk premiums.
3- Extreme weather events
Impact: Effects to service continuity, performance standards, and contract affordability.
Why this cannot be addressed upfront: It is not possible to price or fully mitigate all operational and financial impacts upfront without introducing disproportionate cost or risk premiums.
There is a possibility that the contract may require modification if one of the identified risks above materialise
View 4-notice timelineLatest notice released 25 Sept 2026
Local GovernmentUpdate 3 notices
Temporary Accommodation Scheme
Castle Point Borough Council are seeking an experienced contractor to develop a site in Thundersley into temporary accommodation on a design and build basis.
The works comprise the design development (from RIBA Stage 3 Plus onwards, based on the existing architectural drawings only), construction, completion and handover of site.
The scope includes, but is not limited to, detailed design development, procurement, construction, commissioning, testing, certification and achievement of practical completion, together with all works necessary to deliver a fully functional, compliant and complete development in accordance with all applicable statutory requirements, the employer's requirements and the contract documents.
Further planning work arising from awarded contractors design development value engineering proposals, utility diversions or abnormal connection upgrades (including temporary construction power), and any works outside the agreed red line boundary.