5496 - St. Gwladys Primary School - Lintel Replacement & Associated Works
You are invited to submit a tender for the Replacement of defective lintels at St Gwladys Primary School. The scope of the project is fully described in the drawings and schedules of works but in summary the scope is:
• Replacement of defective lintels and associated works
• Provide internal scaffolding, remove existing suspended ceilings to rooms 078 and 063
• Provide temporary support and replace defective timber lintels with concrete lintels.
• Provide timber treatment to any remaining timber left insitu
• Hack off all defective plaster and replaster, redecorate to match existing
• Provide external scaffolding, remove all defective stonework above existing stone lintels, provide new cavity trays and reinstate existing stonework and make good on completion including repointing
• Take out defective windows and replace like for like with mechanical operators to open windows in room 078
Key Dates:
Construction Start:
13/07/2026
Duration:
4 weeks
5485 - Ty Sign Primary School - Alterations to Outside SRB Area
You are invited to submit a tender for the Alterations to the Outdoor space of the SRB unit at Ty Sign Primary School. The scope of the project is fully described in Appendix 1 but in summary the scope is:
• Prepare surface to receive soft play crumb.
• Supply and fit shelter as described.
• All work to be completed by August 7th 2026.