Loading page content…
Loading page content…
Loading contract search results…
Loading contract details…
| Source: | Contracts Finder |
| Notice Type: | Tender notice |
| Buyer: | Sizewell C Limited |
| Main Category: | Goods |
| Procurement Method: | — |
| Tender Status: | Open |
| Estimated Value (ex. VAT): | £10,000,000 |
| Release Date: | 19 November 2026 |
| Application Deadline: | 25 November 2026 |
| Contract Start Date: | 5 May 2027 (Estimated) |
| Contract End Date: |
Ready to bid on this contract?
BidWriter AI writes your tender response in minutes — import this contract in one click.
View Original Notice
Access the full notice on the official portal
🤝 Need a consortium or subcontracting partner?
SMEs & Primes team up to win opportunities like this. Find partners on the board.
The contract will deliver a commissioned, weathertight and operational Pool Bunker above the base slab. The facility will support assembly, welding and inspection activities before modules are transferred to the Nuclear Island. The scope of works includes: • Primary steel frame and crane runway beams. • Rainscreen cladding and industrial doors, with precast cladding retained as the alternative envelope. • Five-section retractable roof. • Secondary steelwork platforms, working levels and access arrangements. • Mechanical, electrical and public health services, including local exhaust ventilation, power, lighting and controls. • Passenger and goods hoists, stair cores and roof access. • Installation and commissioning of three free-issued gantry cranes. • Tented workshop, lightning protection and earthing. • Testing, commissioning, quality records and formal handover. The base slab and the separate site non-destructive testing contract are outside this sourcing strategy. Their interfaces will be defined in the tender documents and managed through the contract programme. The key scope deliverables are: • Completed design to RIBA stage 4 and coordinated construction information. • Approved contractor programme aligned to project milestones. • Constructed and commissioned Pool Bunker, including roof, cranes, platforms, access and building services. • Completed health, safety, quality and assurance records. • Demonstrated interfaces with the base slab, utilities and non-destructive testing arrangements. • Formal handover following operational readiness review. The timescales are as follows: The Pool Bunker is required to support the planned assembly, welding and inspection of pool and tank liner modules before transfer to the Nuclear Island. The current estimated site construction period is: • 40 weeks for the preferred rainscreen and Safe RAD solution. • 46 weeks for the 275 mm precast fallback solution. The current target is for the Pool Bunker to be completed and handed over by 28 February 2028, ready to support the planned assembly, welding and inspection of pool and tank liner modules. The programme is dependent on completion of the base slab and availability of the K10 area and will be revalidated once the K10 release date is confirmed.
Pipeline status
Not addedImports the contract into your BidWriter pipeline · Qualify before you commit to bid
Application Deadline
25 November 2026
7 days left
Estimated Value
£10,000,000
Need help writing this bid?
Our specialists write winning tender responses. Free consultation, no obligation.
Book a free consultation →| 31 October 2028 (Estimated) |
| Contract Duration: | 1.5 years |
| Procurement ID (OCID): | ocds-b5fd17-56721387-b61e-4164-a5d2-3509e5e4cbc9 |
| Notice Reference: | 0a92843d-9da8-4c16-b682-33b5d72727db-922031 |
Apply online