Full refurbishment of the basement toilets at Buckingham Palace.
The works and services for this project will include, in summary:
◼ All preliminaries, access equipment etc. as per industry norms;
◼ Strip-out of existing redundant services, existing board work and debris, as required;
◼ Creation of new, structurally sound, unisex cubicles;
◼ Creation of new services, including ventilation ductwork, fire alarm system, and lighting, as specified in the Architect’s drawings;
◼ All ancillary firestopping and structural repairs, as required; and
◼ Decorations to new doors, partitions and walls, and flooring.
To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=972060097
Construction of Electric Vehicle Chargers at Buckingham Palace
To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=982689264
The objective of this feasibility study is to assess the technical, environmental, and economic viability of implementing a Ground Source Heat Pump (GSHP) system at Buckingham Palace. The study will evaluate site-specific conditions, including geological and hydrological suitability, energy demand profiles, and potential system configurations. It aims to determine whether a GSHP solution can deliver sustainable, low-carbon heating and cooling in alignment with our operational goals and environmental commitments. The outcome will inform decision-making regarding future investment, design, and implementation strategies.
To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=982679065
The contract encompasses all contract service found in Marlborough House. The scope of this contract
includes:
2.1.1 Monitoring, testing, optimisation, planned maintenance & repair works on the items below:
▪ All plant rooms and services within the boundary of the site including daily vigilance
checks, weekly inspections and monthly observation reports. Provision of plantroom
logbooks and maintaining plantroom cleanliness.
▪ All boilers for heating and hot water services including gas safety certificates for
boilers and pipework from meter
▪ Chiller unit and associated air cooled condenser.
▪ All pumps, primary heating, LTHW primary, variable temperature, constant
temperature, sectional heating, chilled water pumps and sump pumps.
▪ Chilled water and LTHW water pressurisation units, expansion vessels and buffer
storage vessels.
▪ Closed water system sampling and maintenance
▪ All VAV ventilation units, ductwork, extraction fans, filters, grilles, intake louvres and
air conditioning units.
▪ All air handling units and fan coil units.
▪ All other heating and cooling emitters and associated valves inside the building.
▪ All pipework and that is used as a conduit for water services, space heating, cooling,
hot water and cold water with all associated gauges and valves.
▪ All drainage pipework within the building, until it meets the first accessible intercept
or manhole, all saniflow units and pumped drainage, external rainwater drainage
gulleys around the building perimeter
▪ All internal and external plumbing services including taps, external bib taps, water
tanks, WCs, calorifiers, sinks, toilets and associated cisterns
▪ All internal and external lighting installations including maintained and non
maintained self contained emergency lighting and central battery emergency lighting
inverters.
▪ Replacement of all internal and external lighting components upon failure such as
lamps, ballasts, diffusers and drivers.
▪ Repair of all fixed electrical devices and appliances e.g hand dryers
▪ Routine repair of all fixed electrical installations and switchgear
ROYAL HOUSEHOLD PROPERTY SECTION
0025/PPTO Page 5 of 24
▪ Planned maintenance of electrical switchgear, including power factor correction
system with DNO attendance
▪ Inspection and testing of water and refrigerant leak detection systems.
▪ Water hygiene maintenance in accordance with RHPS Water Risk Assessment Written
Scheme of control including: water tank chlorination, HWS pasteurisation, shower
head cleaning, tank inspections, tank sampling, sentinel outlet temperature testing,
low use flushing and additional flushing as required by the RHPS legionella sampling
regime.
▪ All fixed and portable commercial and domestic kitchen equipment, including gas
safety certificates, stop button and ventilation interlock testing.
▪ All services within and attached to the Security Gate Lodge, which includes a vehicle
barrier, pedestrian gate release system, vehicle gate height alarm, CCTV system and
the intruder alarm system.
▪ All services in the Queen Alexandra Memorial on Marlborough Road.
Removal of a Roman mosaic followed by production and installation of a replacement mosaic