Purpose of Notice -
The procurement of a Subcontractor for the A417 road widening temporary vehicle restraint system in connection with the A417 Missing Link at Air Balloon.
Scheme Description -
Under the National Highways Limited Regional Delivery Partnership (RDP), we are appointed as the Principal Contractor for the design and construction of a new dual carriageway at the A417 Missing Link at Air Balloon.
The scheme would provide 3.4 miles (5.5km) of new, rural all-purpose dual carriageway for the A417. The new dual carriageway would connect the existing A417 Brockworth bypass with the existing dual carriageway A417 south of Cowley.
Registering Interest -
Interested parties are to register their interest through making contact via guy.hornsey@kier.co.uk.
Purpose of Notice -
The procurement of a Subcontractor for the Vehicle Recovery Services works in connection with the A417 Missing Link at Air Balloon.
Scheme Description -
Under the National Highways Limited Regional Delivery Partnership (RDP), we are appointed as the Principal Contractor for the design and construction of a new dual carriageway at the A417 Missing Link at Air Balloon.
The scheme would provide 3.4 miles (5.5km) of new, rural all-purpose dual carriageway for the A417. The new dual carriageway would connect the existing A417 Brockworth bypass with the existing dual carriageway A417 south of Cowley.
Registering Interest -
Interested parties are to register their interest through making contact via guy.hornsey@kier.co.uk.
Kier Transportation are looking to engage experienced and qualified contractors to carry out works pertaining to Sheet Piling - Schemes 1 & 2 on the A66 Northern Trans-Pennine scheme. The A66 upgrade will see single-lane sections of the 80km stretch between the M6 and the A1 made into dual carriageway, while key junctions will be improved. The A66 project is to be delivered in collaboration by three Tier 1 contractors, Balfour Beatty, Kier and Keltbray.
We will use the Build UK Common Assessment Criteria (CAS) to ensure a consistent minimum business competence. If your company possesses necessary qualifications and is interested in bidding for this project, please email Transportationprocurement@kier.co.uk with your company's portfolio, relevant experience, and references for further evaluation.
Kier Transportation are looking to engage experienced and qualified contractors to carry out works pertaining to the Schemes 1, 2 and 6 Site & Welfare Cleaning Services on the A66 Northern Trans-Pennine scheme site and compounds.
The A66 upgrade will see single-lane sections of the 80km stretch between the M6 and the A1 made into dual carriageway, while key junctions will be improved. The A66 project is to be delivered in collaboration by three Tier 1 contractors, Balfour Beatty, Kier and Keltbray.
We will use the Build UK Common Assessment Criteria (CAS) to ensure a consistent minimum business competence. If your company possesses necessary qualifications and is interested in bidding for this project, please email Transportationprocurement@kier.co.uk with your company's portfolio, relevant experience, and references for further evaluation.
Kier Transportation are looking to engage experienced and qualified Suppliers for the Welfare Hire, Installation and Removal on the A66 Northern Trans-Pennine scheme.
The A66 upgrade will see single-lane sections of the 80km stretch between the M6 and the A1 made into dual carriageway, while key junctions will be improved. The A66 project is to be delivered in collaboration by three Tier 1 contractors, Balfour Beatty, Kier and Keltbray.
We will use the Build UK Common Assessment Criteria (CAS) to ensure a consistent minimum business competence. If your company possesses necessary qualifications and is interested in bidding for this project, please email Transportationprocurement@kier.co.uk with your company's portfolio, relevant experience, and references for further evaluation.
Kier Transportation are looking to engage an experienced and qualified contractor to carry out works pertaining to Noise and Vibration Monitoring on the A66 NTP.
We will use the Build UK Common Assessment Criteria (CAS) to ensure a consistent minimum business competence. If your company possesses necessary qualifications and is interested in bidding for this project, please email Transportationprocurement@kier.co.uk with your company's portfolio, relevant experience, and references for further evaluation.
Kier Transportation are looking to engage an experienced and qualified service consultant to carry out works pertaining to Construction Contract Management Software on the A66 NTP.
We will use the Build UK Common Assessment Criteria (CAS) to ensure a consistent minimum business competence. If your company possesses necessary qualifications and is interested in bidding for this project, please email Transportationprocurement@kier.co.uk with your company's portfolio, relevant experience, and references for further evaluation.
Kier Transportation require a Subcontractor to undertake Geophysical Survey services.
A geophysical survey is required to determine the bedrock profile and changes in physical properties of the materials to inform piling design in the central reservation.
Boreholes in the area show a large discrepancy of levels over comparatively short distances.
Non-intrusive testing is proposed to determine the rock levels where the physical GI was not undertaken. Note that works are undertaken on the M6 motorway in the Lune Gorge which is why the non-intrusive surveys are proposed.
We will use the Build UK Common Assessment Criteria (CAS) to ensure a consistent minimum business competence. If your company possesses necessary qualifications and is interested in bidding for this project, please email Transportationprocurement@kier.co.uk with your company's portfolio, relevant experience, and references for further evaluation.
Kier Transportation are looking to engage experienced and qualified contractors to provide water monitoring and sampling requirements on 10 designated points as specified on the M6 Lune Gorge project.
Frequency: Monthly - requirement for company awarded tender to attend site monthly to collect samples.
Monitoring requirements: The following parameters shall be laboratory tested for monthly
- pH
- electrical conductivity
- total suspended solids
- dissolved oxygen
- turbidity
- redox potential
- bicarbonate alkalinity
- total and dissolved organic carbon
- metal suite (dissolved and totals): aluminium, arsenic, cadmium, copper, lead, zinc
- major ions: calcium, chloride, sulphate, potassium, sodium
- nitrate
- phosphate
- Total Petroleum Hydrocarbons (TPH) (speciated, aliphatic and aromatic split)
- Polycyclic Aromatic Hydrocarbons (16 PAHs)
We will use the Build UK Common Assessment Criteria (CAS) to ensure a consistent minimum business competence. If your company possesses necessary qualifications and is interested in bidding for this project, please email Transportationprocurement@kier.co.uk with your company's portfolio, relevant experience, and references for further evaluation.
Kier Transportation intends to engage experienced and qualified contractors to undertake works associated with manned security across A66 NTP. The appointed contractor will be responsible for providing a reliable and professional security presence to protect our assets, property, personnel, and visitors outside of standard working hours.
We will use the Build UK Common Assessment Criteria (CAS) to ensure a consistent minimum business competence. If your company possesses necessary qualifications and is interested in bidding for this project, please email Transportationprocurement@kier.co.uk with your company's portfolio, relevant experience, and references for further evaluation.