Program - Works to be carried out between 25 July 2022 and 20/01/23 [26 weeks]. It should be noted that the temporary/permanent deck element of the building project must be completed by 20 August 2022.
Location - Atrium and adjacent plant room areas at Milton College; Chaffron Way Campus
Woughton Campus West, Leadenhall, MK6 5LP.
Works - to install a temporary [or permanent] crash deck floor above the second-floor gantry level of the atrium; to install a sacrificial waterproof deck on the floor and install guttering & storm water drainage; to form a new access to the plantrooms/floor; strip out redundant ventilation plant; new plant room works; removal of the atrium glazing; pigeon protection works.
Contract/procurement - Single stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - 20 June 2022 - 15 July 2022
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
Tender packs are available from Craig Pullen (craig@cpconsulting.org.uk)
Site visits are available on 4th, 5th & 8th July - details are in the tender pack.
Additional information: Tender packs are available from Craig Pullen (craig@cpconsulting.org.uk)
Program - Works to be carried out between 9 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown].
The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods:
Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown]
Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP.
Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections];
Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - First Stage Tender - 09 Sept 2022 - 13 October 2022 [5 weeks]
Adjudication & contractor interviews - 14 October - 3 November 2022 [2 weeks]
Second Stage Tender - 4 November 2022 - 15 December 2022. [6 weeks]
Adjudication & contractor appointment - 15 December - 23 December 2022.
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
Please contact Craig Pullen (craig@cpconsulting.org.uk) to express an interest
Additional information: Tender packs can be obtained via Craig Pullen (craig@cpconsulting.org.uk)
Isles of Scilly Seabird Recovery Project -Operational Plan
The Isles of Scilly Wildlife Trust, as lead partner in the Isles of Scilly Seabird Recovery Project (SRP), is developing a programme of work to clear rats from Bryher, Tresco, St Martin's and the surrounding uninhabited islands. Following on from successful rat eradication of St Agnes and Gugh in 2013, the SRP will enable all of the off-isles of the Isles of Scilly to be cleared of rats, to enable recolonisation and population growth by seabirds, particularly Manx shearwaters and storm petrels.
An experienced contractor is required to write an Operational Plan to record in detail the logistic steps that would be required for the eradication by a principal contractor, including estimates of labour, time, boating and accommodation requirements, and an appropriate resulting estimate of the cost of a full eradication.
This work is to be undertaken between January - March 2025
Additional information: Please contact Craig Pullen (craig@cpconsulting.org.uk) for the tender pack.