Milton Keynes College is seeking a first stage tender for the creation of an Institute of Technology campus at Bletchley Campus. The project comprises the full internal & external refurbishment of The Andrew Peck Building, plus a four-storey extension and external works. The project is fully funded by the DfE.
The existing Andrew Peck Building (APB) with the addition of an extension will increase the overall GIA of the building to around 3990m2. The new higher education Institute of Technology centre will deliver innovative, employer focussed Digital Technology qualifications as part of the South Central Institute of Technology
Additional information: Tender packs can be obtained from Craig Pullen (craig@cpconsulting.org.uk)
Procurement of IT Technology equipment for the South-Central Institute of Technology
Milton Keynes College and Activate Learning are education provider partners developing the South-Central Institute of Technology working with the Department of Education. The South-Central Institute of Technology is a three-site development based in Reading, Oxford and Milton Keynes with Oxford and Bletchley going live in September 22.
This tender is only pertinent to the Oxford site. Oxford Blackbird Leys Technology Campus is in Blackbird Leys Oxford. As part of the development the project requires the installation of IT equipment in a newly refurbished building V Block which has 4 floors. This tender requires the contractor to procure and deliver the IT equipment to all floors of Oxford Blackbird Leys Technology Campus for installation.
The work to install the IT equipment needs to start at 08:00 am on 8th Aug 22 and be complete by 19th Aug 2022 at the Oxford Blackbird Leys Technology Campus therefore the delivery schedules must be coordinated with the project team to ensure a structured installation program is carried out.
Additional information: Tender packs can be obtained from Craig Pullen at craig@cpconsulting.org.uk
Procurement of IT Technology equipment for the South-Central Institute of Technology
Milton Keynes College and Activate Learning are education provider partners developing the South-Central Institute of Technology working with the Department of Education. The South-Central Institute of Technology is a three-site development based in Reading, Oxford, and Milton Keynes.
This tender is only pertinent to the Milton Keynes Site Only
SCIoT Bletchley Campus Located in Milton Keynes at Milton Keynes College Bletchley Campus. As part of the development the project requires the installation of IT equipment for the newly refurbed building which has 4 floors. This tender requires the contractor to procure, deliver and install the IT equipment to the SCIOT Bletchley Campus.
The work to install the IT and Gaming equipment will be a two phases approach, Installation of Gaming equipment needs to start at 08:00 am on Monday 8th Aug 22 and be complete by 19th August 2022. Installation of IT equipment will need to be confirmed between the project team and contractor therefore the delivery schedule must be coordinated with the project team to ensure a structured installation program is carried out.
All deliveries / work must be carried out sensitively and with extreme care as Bletchley College campus is active, there will be staff on site. There is good access to the site at Bletchley Campus there is also the use of a goods service lift to the All Floors in the building for contractors.
Full drawings are included within the tender pack along with contact details of key individuals to provide instruction and responses to queries during the fit-out period.
Additional information: Tender packs can be obtained from Craig Pullen at craig@cpconsulting.org.uk
Program - Works to be carried out between 25 July 2022 and 20/01/23 [26 weeks]. It should be noted that the temporary/permanent deck element of the building project must be completed by 20 August 2022.
Location - Atrium and adjacent plant room areas at Milton College; Chaffron Way Campus
Woughton Campus West, Leadenhall, MK6 5LP.
Works - to install a temporary [or permanent] crash deck floor above the second-floor gantry level of the atrium; to install a sacrificial waterproof deck on the floor and install guttering & storm water drainage; to form a new access to the plantrooms/floor; strip out redundant ventilation plant; new plant room works; removal of the atrium glazing; pigeon protection works.
Contract/procurement - Single stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - 20 June 2022 - 15 July 2022
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
Tender packs are available from Craig Pullen (craig@cpconsulting.org.uk)
Site visits are available on 4th, 5th & 8th July - details are in the tender pack.
Additional information: Tender packs are available from Craig Pullen (craig@cpconsulting.org.uk)
Isles of Scilly Seabird Recovery Project -Operational Plan
The Isles of Scilly Wildlife Trust, as lead partner in the Isles of Scilly Seabird Recovery Project (SRP), is developing a programme of work to clear rats from Bryher, Tresco, St Martin's and the surrounding uninhabited islands. Following on from successful rat eradication of St Agnes and Gugh in 2013, the SRP will enable all of the off-isles of the Isles of Scilly to be cleared of rats, to enable recolonisation and population growth by seabirds, particularly Manx shearwaters and storm petrels.
An experienced contractor is required to write an Operational Plan to record in detail the logistic steps that would be required for the eradication by a principal contractor, including estimates of labour, time, boating and accommodation requirements, and an appropriate resulting estimate of the cost of a full eradication.
This work is to be undertaken between January - March 2025
Additional information: Please contact Craig Pullen (craig@cpconsulting.org.uk) for the tender pack.