This project comprises the development of the newly acquired North campus be developed to include: the construction of the new Industry Hub building; as well the construction of new infrastructure and landscaping elements.
The proposed works will be procured through a single stage Design & Build route, based on RIBA Stage 4 Design information.
The Works will be instructed in two phases:
• Phase 1 being the delivery of the infrastructure and landscaping package only; and
• Phase 2 being the delivery of the infrastructure and landscaping package, as well as the a new Industry Hub building.
The proposed works noted under Phase 2, notably the construction of the new Industry Hub building will be dependent upon a successful funding applications.